BEFREN

Platform on hotel management, interior design and design in Flanders
Construct quickly and efficiently. 5-star Van der Valk
Van der Valk hotel Schiedam is almost finished.

Building quickly and efficiently. 5-star Van der Valk

In Schiedam, the very last touches are being made to the newest Van der Valk hotel, which has been delivered shell, wind and watertight by Van Omme & De Groot. The hotel has 179 rooms, 5 suites, a conference capacity for 400 people, 10 conference rooms, a large restaurant, a sky bar and wellness. It is the first Van der Valk hotel for Van Omme & De Groot with a five-star BREEAM certification.

Stone strips are glued on the eaves and prefabricated balconies.

"At the end of 2018, we were commissioned by Van der Valk. In October 2021, we were able to deliver the building shell, wind- and watertight," says work planner Arnoud van Broekhoven. "We have completed several hotels for Van der Valk, including in Duiven and Dordrecht, but this was the first project with BREEAM 'Outstanding'." To achieve this BREEAM certification, several requirements had to be met. "All the requirements are in a thick book. For example, the origin of all materials had to be substantiated. Also, all wood had to be FSC certified. In addition, waste management on the construction site was an important element."

Dismantling could start earlier.

"The building is fairly similar in construction to the hotels in Duiven and Dordrecht, but the architect made slightly different choices for the facade. For instance, the eaves and prefab balconies with parapets are made of prefabricated concrete with stone strips glued on. We had to be able to prove that the stone strips would remain in place for 50 years and pose no danger to the environment. Using a mathematical model, we were able to calculate the risk, and we also agreed with the client that a random inspection would take place every year."

Van Omme & De Groot at work.

Winning time by investing

The biggest challenge in this construction, however, was the logistics, says the work planner. "In previous projects, the finishing work often did not start until we had completed the shell. Together with Van der Valk, we decided to start the finishing work sooner now, which ultimately saved us 5 to 6 months. We placed the window frames with glass with the structural shell. This was logistically necessary, but a risk. Fortunately, by carefully covering everything, little window damage occurred. The advantage was that all (finishing) parties could work behind the carcass for a shorter period of time. Moreover, it was much more pleasant for the construction workers to work in an enclosed space."

To get all the materials into place, a temporary construction lift was used during the structural work, but the final lifts ín the building were also soon used. "Often the definitive lifts are not built until the structural work is finished. At Van der Valk Schiedam, we chose to build three of the four lifts from the basement to the 10th floor first. During the same period, the concrete shell was completed and the lift installer needed 'only' six weeks to extend the lifts to the 16th floor. The client did pay a bit more for this, but this choice provided a great advantage for the pace of completion."

"*" indicates required fields

Send us a message

This field is for validation purposes and should be left unchanged.

Wij gebruiken cookies. Daarmee analyseren we het gebruik van de website en verbeteren we het gebruiksgemak.

Details

Kunnen we je helpen met zoeken?